AN important two year project to better manage the flow of water along Gallow Syke in Aireville Park, Skipton, and reduce the risk of flooding to homes and businesses in the west of the town has been completed.
Led by Craven District Council to improve the flow of water along the steam as it passes through the park, the scheme, which is part of a larger £5m regeneration scheme for the town, began in 2020 and was carried out mainly during the coronavirus pandemic, when there were fewer people about.
It has seen the rebuilding of two culvert entrances so water can be stored temporarily during flood events, delaying its release and reducing the impact on the industrial areas around the under re-development Engine Shed Lane and Ings Lane - where the council's new waste centre is under construction. Trees removed as part of the project have been replaced with the planting of more than 700 more.
It is seen as crucial to the economic vitality of the town and has received the support of the area's Local Enterprise Partnership (LEP).
Gallow Syke is a small river and tributary of the River Aire, located to the west of Skipton town centre. Principally in an open channel passing through areas of woodland and grassland, Gallow Syke flows in a southerly direction from north of Gargrave Road, near Aireville Grange, through Aireville Park.
The river then culverts under the canal and areas of residential and industrial land before joining with Ings Beck at the junction of Broughton Road and Ings Lane.
On its way through Aireville Park, Gallow Syke passes through two main culverts – the first under the access road serving Aireville Park and the second where the river exits the park under the Leeds and Liverpool Canal.
Before the work took place, the inlets to both culverts were in poor condition with inadequate 'trash screens' which regularly became obstructed with all manner of debris. After being redesigned, they can better support management of water downstream.
At both locations the inlets to the culverts have been rebuilt with new trash screens, safer walkways for maintenance and materials to help the structure blend with semi-rural surroundings of the park, which is popular with both residents and visitors.
In addition, the inlet to the culvert has been physically restricted in size. In normal flows, this restriction will have no impact on the watercourse, but, during periods of heavy rainfall, the restriction will manage the flow of water downstream.
Over time this water will then drain away through a controlled approach helping to reduce the amount of water flowing into Ings Beck.
In addition to rebuilding of the culvert entrances 700 trees and shrubs have been planted at the site to compensate for the trees, which had to be removed as part of the project. The council says planting of the new trees will help to reduce areas of bare ground and silt being washed downstream.
Designed by the engineering consultancy WSP and built by contractors Galliford Try, the scheme is an important part of the delivery of the £5m Skipton Employment and Housing Growth scheme, funded by the Government’s Local Growth Fund, awarded by the York and North Yorkshire Local Enterprise Partnership (LEP).
Councillor Simon Myers, chairman of Craven District Council and lead member for enterprising Craven, said: “The crucial works carried out is set to contribute to reducing the risk of flooding for homes and businesses in the west of Skipton, and will also contribute to the wider scheme, planned to improve vehicle connectivity around Engine Shed Lane, Ings Lane and Wyvern Park.
"We would like to thank residents for their patience and cooperation while we have been building these vital works.”
David Dickson, Chair of the York and North Yorkshire Local Enterprise Partnership joint assets and infrastructure board, added: “Flood resilience is crucial for economic growth, so we’re pleased to see the completion of these works.
"This is an important component of a wider programme in Skipton focusing on business, employment and housing growth, which the York and North Yorkshire Local Enterprise Partnership secured just under £6m of Local Growth Fund towards a further £20million of infrastructure investment, ahead of future commercial developments.”
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules here