THE A59 at Kex Gill is not set to reopen until after Easter in an update that’s likely to frustrate motorists and businesses.
The road, which is a vital route between Skipton and Harrogate fully closed on February 2 after a crack appeared in the road the week before.
It’s led to a lengthy diversion route for motorists through Otley and Ilkley which will now continue for at least the next few weeks.
Cllr Richard Foster (Conservative, Wharfedale) provided the update at a meeting of Skipton and Ripon councillors this morning (Thursday).
Cllr Foster said there had been a new “slippage” on the hill that needs repairing with contractors now on site.
He added works are still ongoing around Blubberhouses due to the previously found crack. He blamed wet weather for the delays.
He said: “There are lot of affected businesses coming forward and the council is doing what it can and is letting people through when it can.”
The section of the A59 is prone to landslips and last year work began on a major £68.9m realignment of the road. However, the council has insisted that the closure is not related to these works.
Conservative council leader Carl Les, who was observing the meeting, said: “It shows the good decision we took to bypass Kex Gill”.
Cllr Les said the new road will be finished in late 2025.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel